Track Records 2020

PIPELINE SERVICES: PROVISION OF PIPELINE PRE-COMMISSIONING,
COMMISSIONING & DE- COMMISSIONING SERVICES
TRACK RECORD (as of 31st August 2020)

Vol Project Description Pipeline Start Complete CIient Location

1

Provision of Transportation and Installation of Subsea 

Flexible Pipeline and Risers for Layang Development Project (Phase 2)

13”x2.5km from HIP to FPSO

10”x2.5km from FPSO to HIP

11”x4.8km from LWP to FPSO

tba tba Sapura Offshore Sdn Bhd Offshore Sarawak /    Offshore Sabah

2

Provision of Pre-commissioning Services 6” x 4.3KM GL Flowline from ECW-A to CDW-B

6” x 4.3KM WI Flowline from ECW-A to CDW-B

10”x5.2KM FWS Flowline from ECW-A to CDP-A FPSO

tba tba Technip Marine (M) Sdn Bhd Peninsular Water

3

Provision of Pre-commissioning Services for Tembikai Non Asssociated Gas (TNAG) Development Project 12″ x 60km FWS Pipeline from WHP to Berantai FPSO March-2020 On Going Vestigo Petroleum Sdn Bhd Peninsular Water

4

Provision of Pipeline Pre-Commissioning (Phase 2) 12″x19.475km from KSM WHA to ZTG WHA 11-Feb-2020 On Going Sapura Offshore Sdn Bhd Offshore Sarawak / Offshore Sabah

5

Provision of Leak Testing & Flooding Services Leak Test 38″ pulling Head/ Laydown Head Flooding & Preservation 38″ Pipeline & 38″ Riser 01-Dec-19 06-Apr-2020 Sapura Fabrication Sdn Bhd Offshore Sarawak / Offshore Sabah

6

Provision of Temporary Spread Mooring System for TST Station Keeping Including Transportation & Installation Services for TST Sepat DEPS Project (Phase 2) 6″ x 660m from JUR to TST   22-Nov-19 25-Jan-2020 Franklin Offshore / E.A. Technique Peninsular Water

7

Provision of Temporary Spread Mooring System for TST Station Keeping Including Transportation & Installation Services for TST Sepat DEPS Project (Phase 1) 6″ x 660m from JUR to TST 08-Nov-19 18-Nov-19 Franklin Offshore / E.A. Technique  Peninsular Water

8

Provision of Transportation and Installation of Subsea 

Flexible Pipeline and Risers for Layang Development Project (Phase 2)

13”x2.5km from HIP to FPSO

10”x2.5km from FPSO to HIP

11”x4.8km from LWP to FPSO

17-Sept-19 13-Nov-19 Sapura Offshore Sdn Bhd Offshore Sarawak / Offshore Sabah

9

Provision of Pre-commissioning Services for PCSB Project Pipeline Hydrotesting, from Temporary Test

Blind Installed at D35R-A Platform (Top Riser)

to subsea Test Blind Installed at Subsea Tie-In Point KP2.0

1-May-19 14-Jun-19 Sapura Offshore Sdn Bhd Offshore Sarawak / Offshore Sabah

10

Provision of Pre-Commissioning Services for HESS Project Year 2019

Provision of pipeline cleaning, gauging, flooding, hydrotesting, dewatering, air drying & nitrogen packing (Phase 1)

12″x19.475km FWS Pipeline from Bunga Zetung WHP-Bunga Kesumba WHP 28-May-19 8-July-19 HESS Exploration & Production Malaysia BV / Sapura Offshore Sdn Bhd Offshore Sarawak / Offshore Sabah

11

Provision of Pre-Commissioning Services for PCSB P6 Project Year 2019

Provision of Pre-Commissioning (cleaning, gauging, filling

and hydrotesting) – subsea to top of riser for sectional pipeline replacement

PL293: 16″x2km D35R-A to Subsea 2-May-19 28-May-19 Petronas Carigali Sdn Bhd / Sapura Offshore Sdn Bhd Offshore Sarawak / Offshore Sabah

12

Installation of Subsea Pipeline Works at Gulf of Suez Provision of Leak Testing for Pulling Heads at SOEB 3nos. 18″, 1no. 12″ and 2nos. 8″ 2-Mar-19 10-Mar-19 Sapura Offshore Sdn Bhd Offshore Sarawak / Offshore Sabah

13

PFLNG1 Relocation

Decommissioning (Deoiling, Flushing, Dewatering, Nitrogen Drying & Nitrogen Packing) for existing flowline. Precommissioning (Cleaning, Gauging, Filling, Leak Testing, Riser Annulus Vacuum Testing, Dewatering, Nitrogen Drying & Nitrogen Packing) for new flowline.

10″x3.5km KAKG-A to PFLNG1 (Existing) 10×5.7km KBB to PFLNG1 (New) 10-Nov-18 29-Apr-19 Petronas Floating LNG1 (L) Ltd

/ DelSol Offshore Sdn Bhd/ Starke Marine Sdn Bhd

Offshore Sarawak / Offshore Sabah

14

Pipeline Inspection – Eddy Current CAM Pig inspection with product 16″x16km Oil Pipeline Gu-A/Tap-A 22-Oct-18 12-Nov-18 ExxonMobil Exploration & Production Malaysia Inc / Armada Technology Offshore Terengganu, Malaysia

15

Pipeline Inspection Support Service – Line proving, aggressive cleaning (wax removal) and assist InLine Inspection Tool pumping PID 1101: 8″x0.7km Oil Pipeline SEMN21L to STG30L 15-Oct-18 9-Nov-18 Brunei Shell Petroleum / Tractor Petroleum Services / J- Rahman Oilfields & Logistics Sdn Bhd Onshore Brunei

16

PAN Malaysia Transportation and Installation of Offshore Facilities (for Year 2017-2018)

SSB 2018 Pipeline – Provision of pipeline pre- commissioning

16″ – Nitrogen re-purging/re-packing

16″x16km E6DPR-E8DRA 1-Oct-18 15-Oct-18 Sarawak Shell Berhad/

Sapura Offshore Sdn Bhd

Offshore Sarawak, Malaysia