PIPELINE SERVICES: PROVISION OF PIPELINE PRE-COMMISSIONING,
COMMISSIONING & DE- COMMISSIONING SERVICES
TRACK RECORD (as of 31st August 2019)
Vol | Project Description | Pipeline | Start | Complete | Client | Location |
1 | Provision of Pre-Commissioning Services for HESS Project Year 2019 Provision of Spool Leak Testing, pipeline flooding, dewatering, air drying & nitrogen packing for Subsea InLine Tee Installation |
12?x19.475km FWS Pipeline from Bunga Zetung WHP-Bunga Kesumba WHP | To Start 12/10/2019 | 35-days | HESS Exploration & Production Malaysia BV / Sapura Offshore Sdn Bhd |
Offshore Kelantan, Malaysia
|
2 | Provision of Transportation and Installation of Subsea Flexible Pipelines and Risers for Layang Development Project Deoiling/Degassing (Water Treatment System), Filling, Leak Testing, Nitrogen Dewatering, Nitrogen Drying, Nitrogen Packing, MEG Swabbing and Riser Annulus Vacuum Testing. |
11?x4.8km ad 13?x3.1km with subsea jumper flexible Flowline from LWP to HIP – Deoiling 10?x2.5km flexible flowline from HIP to FPSO 11?x4.8k flexible flowline from LWP to FPSO 13?x3.1km flexible flowline from HIP to FPSO | 10-Sep-19 | 40-days | JX Nippon Oil & Gas Exploration (Malaysia) Limited / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
3 | Provision of Pre-Commissioning Services for HESS Project Year 2019 Provision of Spool Leak Testing, pipeline cleaning, gauging, flooding (subsea-subsea), hydrotesting (subsea- topside), dewatering, air drying & nitrogen packing |
12?x19.475km FWS Pipeline from Bunga Zetung WHP-Bunga Kesumba WHP | 6-Jun-19 | 2-Jul-19 | HESS Exploration & Production Malaysia BV / Sapura Offshore Sdn Bhd |
Offshore Kelantan, Malaysia
|
4 | Provision of Pre-Commissioning Services for PCSB P6 Project Year 2019 Provision of Pre-Commissioning (cleaning, gauging, filling and hydrotesting) – subsea to top of riser for sectional pipeline replacement |
PL293: 16?x2km D35R-A to Subsea | 2-May-19 | 28-May-19 | Petronas Carigali Sdn Bhd / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
5 | Installation of Subsea Pipeline Works at Gulf of Suez Provision of Leak Testing for Pulling Heads at SOEB | 3nos. 18?, 1no. 12? and 2nos. 8? | 2-Mar-19 | 10-Mar-19 | Sapura Offshore Sdn Bhd |
Onshore Johor, Malaysia
|
6 | PFLNG1 Relocation Decommissioning (Deoiling, Flushing, Dewatering, Nitrogen Drying & Nitrogen Packing) for existing flexible flowline. Precommissioning (Cleaning, Gauging, Filling, Leak Testing, Riser Annulus Vacuum Testing, Dewatering, Nitrogen Drying & Nitrogen Packing) for new flexible flowline. |
10?x3.5km KAKG-A to PFLNG1 (Existing) 10×5.7km KBB to PFLNG1 (New) | 10-Nov-18 | 29-Apr-19 | Petronas Floating LNG1 (L) Ltd / DelSol Offshore Sdn Bhd/ Starke Marine Sdn Bhd |
Offshore Sarawak / Offshore Sabah
|
7 | PAN Malaysia Transportation and Installation of Offshore Facilities (for Year 2017-2018) Anjung Pipeline – Provision of pipeline wet buckle contingency flushing and dewatering |
18″x8.5km Condensate Gas Pipeline AJJT-A to KAKG-A CRA coated | 5-Sep-18 | 16-Nov-18 | Petronas Carigali Sdn Bhd / Sapura Offshore Sdn Bhd | Offshore Sarawak, Malaysia |
8 | Provision of Pipeline Flushing Services for F23 SW Removal Work for SSB Project Year 2018 | 12″x7.1km Condensate Gas Pipeline Flushing (hydrocarbon removal) from Subsea Wellhead to F23DP-A Platform | 29-Aug-18 | 11-Sep-18 | Sarawak Shell Berhad / Sapura Offshore Sdn Bhd | Offshore Sarawak, Malaysia |
9 | EPCC for Prai Terminal Diesel Subsea Pipeline Replacement – Provision of pipeline cleaning, gauging, floding and hydrotesting | 10″ x 900m Rigid Pipeline from Onshore Terminal to Offshore Offloading Terminal | 28-Aug-18 | 12-Sep-18 | Chevron Malaysia Limited / HSAP Sdn Bhd | Onshore/Offshore Penang, Malaysia |
10 | Flexible Flowline, Riser and Export Hose Pre- Commissioning for FSO Mekar Bergading – Provision of Filling and Leak Testing | 6″x2.5km Condensate Gas Flexible flowline WHHP Platform to FSO Mekar Bergading 16″x300m Export Hose from FSO Mekar Bergading to Floating End | 7-Jul-18 | 31-Jul-18 | Hess E&P / Franklin Offshore International Pte Ltd / Starke Marine Sdn Bhd | Offshore Terengganu, Malaysia |
11 | PAN Malaysia Transportation and Installation of Offshore Facilities (for Year 2017-2018) SSB 2018 Pipeline – Provision of pipeline pre- commissioning 10″&16″ – Spool testing, flooding for tie-in, cleaning, gauging, filling and hydrotesting 16″ – Dewatering, air drying and nitrogen purging/packing |
10″x68km E6DPA-D35DRA, 16″x16km E6DPR-E8DRA |
20-Jun-18 | 20-Aug-18 | Sarawak Shell Berhad / Sapura Offshore Sdn Bhd | Offshore Sarawak, Malaysia |
12 | SEPAT and Riser Temporary Disengagement and Hook- Up Campaign for Petronas Carigali Sdn Bhd – Provision of Fleaible Flowline Flushing/Pigging, Leak Testing and Annulus Vacuum Testing | 6″x200m Crude Oil Flexible WHHP Platform to Sepat A FSO | 4-Jun-18 | 21-Jun-18 | Petronas Carigali Sdn Bhd / Fame Klaut Sdn Bhd / Starke Marine Sdn Bhd | Offshore Terengganu, Malaysia |
13 | Ultrasonic Intelligent Pigging Inspetion for Gas Lift Pipelines – Provision of equipment and personnel for pipeline cleaning, auxiliary pumping for UTIP, dewatering, air drying an dnitrogen packing. | 4″x20km EBA Platform to CHRA Platform 4″x7.5km EBA Platform to WBA Platform | 18-Apr-18 | 21-May-18 | Sapura Exploration & Production (PM) Ltd / Quest Integrity | Offshore Terengganu, Malaysia |
14 | Pengerang Development Project: Provision of pumps and accessories to support filling and testing of sphere tanks | 2nos Sphere Tanks | 22-Jan-18 | 10-Mar-18 | Punj Llyod / Sceptre Power Sdn Bhd | Onshore Johor, Malaysia |
15 | Crude Oil Transfer for West Desaru Pipeline: Supply of oil discharge hoses and fittings for crude ol transfer | 8″ x 12km West Desaru Platform to FPSO | 8-Feb-18 | 8-Feb-18 | Petrofac Limited / Amaniaga Resources Sdn Bhd | Offshore Terengganu, Malaysia |