PIPELINE SERVICES: PROVISION OF PIPELINE PRE-COMMISSIONING,
COMMISSIONING & DE- COMMISSIONING SERVICES
TRACK RECORD (as of 31st August 2019)
Vol | Project Description | Pipeline | Start | Complete | Client | Location |
1 | PFLNG1 Relocation Decommissioning (Deoiling, Flushing, Dewatering, Nitrogen Drying & Nitrogen Packing) for existing flexible flowline. Precommissioning (Cleaning, Gauging, Filling, Leak Testing, Riser Annulus Vacuum Testing, Dewatering, Nitrogen Drying & Nitrogen Packing) for new flexible flowline. |
10″x3.5km KAKG-A to PFLNG1 (Existing) 10×5.7km KBB to PFLNG1 (New) | 10-Nov-18 | 29-Apr-19 | Petronas Floating LNG1 (L) Ltd / DelSol Offshore Sdn Bhd/ Starke Marine Sdn Bhd |
Offshore Sarawak / Offshore Sabah
|
2 | Pipeline Inspection – Eddy Current CAM Pig inspection with product | 16″x16km Oil Pipeline Gu-A/Tap-A | 22-Oct-18 | 12-Nov-18 | ExxonMobil Exploration & Production Malaysia Inc / Armada Technology |
Offshore Terengganu, Malaysia
|
3 | Pipeline Inspection Support Service – Line proving, aggressive cleaning (wax removal) and assist InLine Inspection Tool pumping | PID 1101: 8″x0.7km Oil Pipeline SEMN21L to STG30L | 15-Oct-18 | 9-Nov-18 | Brunei Shell Petroleum / Tractor Petroleum Services / J- Rahman Oilfields & Logistics Sdn Bhd | Onshore Brunei |
4 | PAN Malaysia Transportation and Installation of Offshore Facilities (for Year 2017-2018) SSB 2018 Pipeline – Provision of pipeline pre- commissioning 16″ – Nitrogen re-purging/re-packing |
16″x16km E6DPR-E8DRA | 1-Oct-18 | 15-Oct-18 | Sarawak Shell Berhad / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
5 | PAN Malaysia Transportation and Installation of Offshore Facilities (for Year 2017-2018) Anjung Pipeline – Provision of pipeline wet buckle contingency flushing and dewatering |
18″x8.5km Condensate Gas Pipeline AJJT-A to KAKG-A CRA coated | 5-Sep-18 | 16-Nov-18 | Petronas Carigali Sdn Bhd / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
6 | Provision of Pipeline Flushing Services for F23 SW Removal Work for SSB Project Year 2018 | 12″x7.1km Condensate Gas Pipeline Flushing (hydrocarbon removal) from Subsea Wellhead to F23DP-A Platform | 29-Aug-18 | 11-Sep-18 | Sarawak Shell Berhad / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
7 | EPCC for Prai Terminal Diesel Subsea Pipeline Replacement – Provision of pipeline cleaning, gauging, flooding and hydrotesting | 10″ x 900m Rigid Pipeline from Onshore Terminal to Offshore Offloading Terminal | 28-Aug-18 | 12-Sep-18 | Chevron Malaysia Limited / HSAP Sdn Bhd |
Onshore/Offshore Penang, Malaysia
|
8 | Flexible Flowline, Riser and Export Hose Pre- Commissioning for FSO Mekar Bergading – Provision of Filling and Leak Testing | 6″x2.5km Condensate Gas Flexible flowline WHHP Platform to FSO Mekar Bergading 16″x300m Export Hose from FSO Mekar Bergading to Floating End | 7-Jul-18 | 31-Jul-18 | Hess E&P / Franklin Offshore International Pte Ltd / Starke Marine Sdn Bhd |
Offshore Kelantan, Malaysia
|
9 | PAN Malaysia Transportation and Installation of Offshore Facilities (for Year 2017-2018) SSB 2018 Pipeline – Provision of pipeline pre- commissioning 10″&16″ – Spool testing, flooding for tie-in, cleaning, gauging, filling and hydrotesting 16″ – Dewatering, air drying and nitrogen purging/packing |
10″x68km E6DPA-D35DRA, 16″x16km E6DPR-E8DRA | 20-Jun-18 | 20-Aug-18 | Sarawak Shell Berhad / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
10 | SEPAT and Riser Temporary Disengagement and Hook- Up Campaign for Petronas Carigali Sdn Bhd – Provision of Flexible Flowline Flushing/Pigging, Leak Testing and Annulus Vacuum Testing | 6″x200m Crude Oil Flexible WHHP Platform to Sepat A FSO | 4-Jun-18 | 21-Jun-18 | Petronas Carigali Sdn Bhd / Fame Klaut Sdn Bhd / Starke Marine Sdn Bhd |
Offshore Terengganu, Malaysia
|
11 | Ultrasonic Intelligent Pigging Inspetion for Gas Lift Pipelines – Provision of equipment and personnel for pipeline cleaning, auxiliary pumping for UTIP, dewatering, air drying an dnitrogen packing. | 4″x20km EBA Platform to CHRA Platform 4″x7.5km EBA Platform to WBA Platform | 18-Apr-18 | 21-May-18 | Sapura Exploration & Production (PM) Ltd / Quest Integrity |
Offshore Terengganu, Malaysia
|
12 | Pengerang Development Project: Provision of pumps and accessories to support filling and testing of sphere tanks | 2nos Sphere Tanks | 22-Jan-18 | 10-Mar-18 | Punj Llyod / Sceptre Power Sdn Bhd |
Onshore Johor, Malaysia
|
13 | Crude Oil Transfer for West Desaru Pipeline: Supply of oil discharge hoses and fittings for crude ol transfer | 8″ x 12km West Desaru Platform to FPSO | 8-Feb-18 | 8-Feb-18 | Petrofac Limited / Amaniaga Resources Sdn Bhd |
Offshore Terengganu, Malaysia
|
14 | Crude Oil Transfer for West Desaru Pipeline: Provision of personnel and equipment for transfering of crude oil from platform back to FPSO during pig stuck recovery | 8″ x 12km West Desaru Platform to FPSO | 6-Jan-18 | 22-Jan-18 | Petrofac Limited / Amaniaga Resources Sdn Bhd |
Offshore Terengganu, Malaysia
|
15 | Laying of Gas Transmission Pipeline from Meranti View to Banyan Avenue in Jurong Island: Provision of personnel and equipment for MFL pig stuck recovery | 28″ x 6km SLNG Pipeline from Meranti View to Banyan Avenue | 1-Jan-18 | 10-Jan-18 | WEC Engineers & Constructors Pte Ltd / SP Group / H Rosen Engineering |
Onshore Jurong Island, Singapore
|