PIPELINE SERVICES: PROVISION OF PIPELINE PRE-COMMISSIONING,
COMMISSIONING & DE- COMMISSIONING SERVICES
TRACK RECORD (as of 31st August 2019)
Vol | Project Description | Pipeline | Start | Complete | Client | Location |
1 | Provision of Pre-Commissioning Services for HESS Project Year 2019 Provision of Spool Leak Testing, pipeline flooding, dewatering, air drying & nitrogen packing for Subsea InLine Tee Installation |
12″x19.475km FWS Pipeline from Bunga Zetung WHP-Bunga Kesumba WHP | To Start 12/10/2019 | 35-days | HESS Exploration & Production Malaysia BV / Sapura Offshore Sdn Bhd |
Offshore Kelantan, Malaysia
|
2 | Provision of Transportation and Installation of Subsea Flexible Pipelines and Risers for Layang Development Project Deoiling/Degassing (Water Treatment System), Filling, Leak Testing, Nitrogen Dewatering, Nitrogen Drying, Nitrogen Packing, MEG Swabbing and Riser Annulus Vacuum Testing. |
11″x4.8km ad 13″x3.1km with subsea jumper flexible Flowline from LWP to HIP – Deoiling 10″x2.5km flexible flowline from HIP to FPSO 11″x4.8k flexible flowline from LWP to FPSO 13″x3.1km flexible flowline from HIP to FPSO | 10-Sep-19 | 40-days | JX Nippon Oil & Gas Exploration (Malaysia) Limited / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
3 | Provision of Pre-Commissioning Services for HESS Project Year 2019 Provision of Spool Leak Testing, pipeline cleaning, gauging, flooding (subsea-subsea), hydrotesting (subsea- topside), dewatering, air drying & nitrogen packing |
12″x19.475km FWS Pipeline from Bunga Zetung WHP-Bunga Kesumba WHP | 6-Jun-19 | 2-Jul-19 | HESS Exploration & Production Malaysia BV / Sapura Offshore Sdn Bhd |
Offshore Kelantan, Malaysia
|
4 | Provision of Pre-Commissioning Services for PCSB P6 Project Year 2019 Provision of Pre-Commissioning (cleaning, gauging, filling and hydrotesting) – subsea to top of riser for sectional pipeline replacement |
PL293: 16″x2km D35R-A to Subsea | 2-May-19 | 28-May-19 | Petronas Carigali Sdn Bhd / Sapura Offshore Sdn Bhd |
Offshore Sarawak, Malaysia
|
5 | Installation of Subsea Pipeline Works at Gulf of Suez Provision of Leak Testing for Pulling Heads at SOEB | 3nos. 18″, 1no. 12″ and 2nos. 8″ | 2-Mar-19 | 10-Mar-19 | Sapura Offshore Sdn Bhd |
Onshore Johor, Malaysia
|
6 | PFLNG1 Relocation Decommissioning (Deoiling, Flushing, Dewatering, Nitrogen Drying & Nitrogen Packing) for existing flexible flowline. Precommissioning (Cleaning, Gauging, Filling, Leak Testing, Riser Annulus Vacuum Testing, Dewatering, Nitrogen Drying & Nitrogen Packing) for new flexible flowline. |
10″x3.5km KAKG-A to PFLNG1 (Existing) 10×5.7km KBB to PFLNG1 (New) | 10-Nov-18 | 29-Apr-19 | Petronas Floating LNG1 (L) Ltd / DelSol Offshore Sdn Bhd/ Starke Marine Sdn Bhd |
Offshore Sarawak / Offshore Sabah
|